Contact Us

Contact us

Are you looking for a job or are you a student looking for an internship?

 

Read more: https://career.veo.fi

What business segment does your matter concern?
Reason for reaching out

Contact info

How do you prefer being contacted?

VEO delivered GIS substation to Savon Voima Verkko

In the summer of 2018, VEO delivered a new substation to Savon Voima Verkko Oy in Iisalmi, Finland. The Paloisvirta 110 kV substation is based on gas-insulated switchgear (GIS) technology and is an important node in the Iisalmi power distribution network.

Why GIS?

Substations based on GIS technology require less space than traditional air-insulated ones as the switchgear can be placed indoors. This also makes it possible to create a nicer looking construction; the Paloisvirta substation, for example, is coated in brick which makes it fit nicely into the urban environment in the centre of Iisalmi.

GIS substations are built on site, as turnkey deliveries. VEO manages everything, starting from the excavation work to the delivery of protection, control and automation equipment. The GIS share of VEO projects keeps growing as an increasing number of customers discover the benefits.

Reliable track record

VEO’s extensive project management skills combined with the best products on the market result in top-quality projects. Savon Voima Verkko has worked with VEO since the beginning of VEO´s history and has continued confidence in the Vaasa-based company.

“Substation construction in an urban environment is always a demanding project. Once again, VEO has proven its reliability.”

“Substation construction in an urban environment is always a demanding project. It is therefore important to have a reliable partner with solid know-how. Once again, VEO has proven its reliability,” says Jussi Antikainen, Planning Manager at Savon Voima Verkko.

The delivered substation is an important node in the Iisalmi power distribution network.